WCT Construction Sdn Bhd was awarded the bulk earthworks contract and successfully moved and handled 50 million cu. m. of earth, representing half the total earthworks at KLIA. Additional works included slope protection, horizontal drainage works and construction of the main platform area and perimeter road and central and northern retention pond.
| PACKAGE EW1 |
Project Components |
|
CLIENT Pilecon Civil Works Sdn Bhd CONTRACT SUM RM 39,841,602
|
Earthworks |
| PACKAGE EW3 |
Project Components |
CLIENT Pati Sdn Bhd CONTRACT SUM RM 10,184,776 |
Site Clearance Earthworks Horizontal Drainage Works
|
| PACKAGE EW3 |
Project Components |
CLIENT Pati Sdn Bhd CONTRACT SUM RM 6,174,680
|
Central Retention Pond |
| PACKAGE EW5 |
Project Components |
CLIENT Percon Corporation Sdn Bhd CONTRACT SUM RM 45,915,781 |
Construction and Completion of the Main Platform Area, Perimeter Road (CH21,000 - CH23,000) & Northern Retention Pond.
|
| PACKAGE EW8 |
Project Components |
CLIENT Seleksi Pilecon JV Sdn Bhd CONTRACT SUM RM 18,049,435
|
Southern Airport Area Earthworks
|
| PACKAGE EW9 |
Project Components |
CLIENT Pembinaan Mitrajaya Sdn Bhd CONTRACT SUM RM 36,376,910
|
Southern Airport Area Earthworks (Perimeter Road) |
Contract value: RM138m
www.klia.com.my |