The contract involves the design and construction of three (3) main systems namely, airfield facilities, tunnel and detention ponds. The airfield facilities with two (2) runways of 4.84km and 4.25km each, three (3) parallel taxiway, aircraft parking aprons, drainage works, airfield ground lighting facilities, four (4) substations and other related facilities, is designed to cater for the latest large body aircrafts.
The structure of the 1km dual three (3) lane midfield access tunnel shall consist of twin cells with a dimension of 20m by 5.5m per cell. This will be constructed complete with mechanical and electrical facilities for power, communication and ventilation system. There will be four (4) detention ponds which will include all necessary power supply and pump station system.
The contract period will end in January 2011 and WCT has a 15% stake in the overall project and undertakes 49% of total works.
Contract Value : QR3.27 billion
To view the Project Details, please log on to : NDIA Project Website.